Looking upstream in outlet conduit from point opposite sta. 13+40 of the outlet conduit. Dragline is placing concrete in invert with a bottom-dump bucket.
Placing concrete in outlet conduit between stations 10+64.17 and 10+96.83. Dump trucks haul concrete from the mixing plant and dump into the hopper which is lowered to the buggy deck with a small dragline.
Looking downstream in outlet channel from sta. 14+50, showing construction of drainage system under the channel floor. Spillway cut is seen in background.
Looking upstream in outlet channel from station 15+50 of spillway. Intersection of outlet channel and spillway in immediate foreground. Refer to Pine R - 166
Looking upstream along centerline of outlet channel. Picture taken at 11:45 AM, a few minutes before water flowed over weir wall. Standing on temporary bulkhead from left to right - C. A. Burns, H. F. Bahmeier, and F. F. Smith.
Looking downstream along centerline of outlet channel from a point on downstream slope of embankment. Pump houses on each side are for contractor's water supply. Refer to Pine R - 233
Excavation at right side of spillway near sta. 7+00. Le Tourneau is removing material which has been bladed off of slope with motor-grader seen in Pine R - 268.